Consolidation Time Calculator

How long settlement takes: t₅₀/t₉₀ from c_v and drainage path.

0
50% settlement (years)
0
90% settlement (years)

Time scales with drainage path SQUARED — halving the path (sand drains/PVDs) quarters the wait. That's the entire business case of wick drains under embankments.

Formula

t = T_v·H_d²/c_v (T₅₀ = 0.197, T₉₀ = 0.848)
References: Terzaghi time factors; ground improvement practice

Consolidation Time Calculator is a free consolidation time for geotechnical engineers and foundation designers — instant, accurate and 100% client-side, with the governing formula and reference shown next to the result so the number can be defended, not just quoted.

About Consolidation Time Calculator

How long settlement takes: t₅₀/t₉₀ from c_v and drainage path. The calculation implements t = T_v·H_d²/c_v (T₅₀ = 0.197, T₉₀ = 0.848) (Terzaghi time factors; ground improvement practice). Time scales with drainage path SQUARED — halving the path (sand drains/PVDs) quarters the wait. That's the entire business case of wick drains under embankments.

How to use Consolidation Time Calculator

  1. 1Enter Layer thickness in m.
  2. 2Enter Drainage (1 single (impermeable base) · 2 double (sand above & below)).
  3. 3Enter Coefficient c_v in m²/yr (Soft clays 1–10 m²/yr).
  4. 4Read 50% settlement, 90% settlement instantly — no submit button needed.
  5. 5Need US units? Flip the SI/Imperial toggle and every field converts.

Why use Consolidation Time Calculator?

  • Implements the standard formula — t = T_v·H_d²/c_v (T₅₀ = 0.197, T₉₀ = 0.848)
  • Reference cited on-page: Terzaghi time factors; ground improvement practice
  • One-click SI ⇄ Imperial toggle — values convert in place, physics stays in SI
  • Live worked example: the substitution recomputes from your numbers
  • Runs entirely in your browser — nothing uploaded, free forever

Frequently asked questions

What formula does the Consolidation Time Calculator use?+

It computes t = T_v·H_d²/c_v (T₅₀ = 0.197, T₉₀ = 0.848), per Terzaghi time factors; ground improvement practice. The formula is displayed under the result along with a worked example substituted with your own inputs.

What should I keep in mind when using this calculator?+

Time scales with drainage path SQUARED — halving the path (sand drains/PVDs) quarters the wait. That's the entire business case of wick drains under embankments.

Can this replace a soil investigation?+

No calculator replaces boreholes and lab tests — but with investigated parameters in hand, this gives you the standard-method result instantly, with the formula shown so reviewers can check it.

Is the Consolidation Time Calculator free to use?+

Yes — completely free, no sign-up, no limits. It runs client-side in your browser, so inputs stay private and results are instant even on slow connections.